NH Route 12 & North Street Improvements Project Update 5-8

May 08, 2025


Claremont 13248
NH Route 12 & North Street Improvements Project
 
*** PLEASE NOTE THAT THE NORTH STREET CLOSURE IS EXTENDED THROUGH  MAY 14, 2025
 
The City of Claremont’s contractor, B.U.R Construction, has resumed construction activities for the 2025 construction season on the NH Route 12 and North Street Improvements Project.
 
Construction activities will include road box construction on North Street. Stormwater drainage construction will resume on May 5, 2025, on NH 12. There will be impacts to traffic with lane closures and one-way alternating traffic during daytime work hours on NH Route 12. North Street will be closed beginning on May 5, 2025, through May 14, 2025. There will be a detour set up while they prepare for and pave this section of the roadway.
 
This Federally funded project involves reconfiguring the NH 12 / North Street intersection and reconstruct, realign, and widen the respective roadway approaches which total approximately 5,200 feet in length. The work will include profile improvements to North Street and a stop-controlled intersection where North Street meets NH 12.
 
Utility adjustments, a new water line, drainage improvements, replacement of the Stevens Brook culvert under NH 12, soldier pile retaining wall construction, and stormwater management measures will also be included in the project.
 
 
 